Federal government construction contractors often times lose a considerable amount of money due to lack of understanding about the available construction delay claims: compensable, excusable delaysConstruction Delays Claim in Government Contracting Under FAR Changes Clause, or concurrent delays.  

Avoiding the painful results from not understanding what is a compensable delay under the FAR can make the difference in whether or not you get paid or win an appeal from the contracting officer’s final decision.

At times, equitable adjustments are available to the contractor under the FAR Changes Clause.  In government construction contracts, companies are entitled to equitable adjustments only for changes ordered or as directed by a contracting officer according to the FAR changes clause.  FAR 52.243(a)-(d).

  • Submitting a claim that does not meet the Contract Disputes Act not only causes the CO’s denial of the claim but also may warrant the Appeals Court Dismissing your case.
  • Construction delay claims preparation can be tricky. Having the best approach will be a benefit because claims accepted by the government include a reasonable explanation of why the claim should be paid and enough detail that can help the CO make the decision to pay.

FAR Government Construction Compensable vs Excusable Delays

When there is a delay on a government project, it is important to distinguish a compensable delay from an excusable delay.  If the government caused or imposed the delay, then the delay may be compensable and both a monetary and a time extension would be due.  M.E.S., Inc. (2012); Edge Const. Co. v. United States, 95 Fed. Cl. 407 (2010). 

However, if the delay was not caused by the government, a contractor is only entitled to an excusable delay, whereby only a time extension is due.  M.E.S., Inc. See also equitable subrogation and Miller Act claims.

Compensable Delay Requirement Under FAR Change Order Clause

In addition to the government’s liability, causation, and resulting injury must also be shown to justify a request for equitable adjustmentServidone Constr. Corp. v. United States, 931 F.2d 860 (Fed. Cir. 1991).  Under the FAR Change Order Clause, the delay must also be unreasonable for it to be compensable.  George Sollitt Constr. Co. v. United States, 64 Fed. Cl. 229 (2005).  Courts look a the facts of each case to decide whether or not the agency’s actions were unreasonable.

Federal Construction Contracts — Excusable Delay Meaning 

Excusable delay on a construction project means that the event causing the delay is not the contractor’s fault. A delay often occurs when there is unusually severe weather.  

Courts have made it clear that while excusable delays may be available for unusually severe weather, equitable adjustments are not available for such delays under the FAR Government Construction Changes Clause.  Edge Const. Co. 

  • The contractor must still provide evidence of the unusually severe conditions before they can be entitled to a time extension.
  • An excusable delay may turn into a compensable delay via a constructive acceleration contract claim if the time extension was requested and then denied.

If the government insisted on a completion within a time frame that did not allow for the extension,  then contractors may find themselves incurring more costs. As a result, the agency may be liable for damages.  Fraser Const. v. United States, 384 F.3d 1354 (Fed. Cir. 2005).

At times, a contractor is unable to complete the project within the originally specified period.  To be considered an excusable delay, once the government proves late completion, the contractor then must show that the delay was excusable.  PCL Constr. Servs., Inc. v. United States, 53 Fed. Cl. 479 (2002).  

One example of such delay is when the government delayed the project and the contractor missed the performance deadline. 

FAR Changes Clause and Concurrent Construction Contract Delays

Under the FAR Changes Clause, even if there are compensable FAR Government construction delays, a contractor typically may not recover if it is concurrent with an additional delay not caused by the government, such as weather or contractor delay.  Fireman’s Fund Ins. Co. v. United States, 92 Fed. Cl. 598 (2010). 

However, a contractor can still attempt to prove that the government-caused delay was distinct from others and should thus still be compensable.  Mega Const. Co. v. United States, 29 Fed. Cl. 396 (1993). See information about cost escalation damages

For all alleged government construction delays, the contractor bears the burden of proof.  This means that you should provide detailed records and evidence to support your position in the event of litigation.

Learn About More Critical Contract Claims and CDA Topics

If you think you may have construction delays claims against the federal government under the FAR Changes Clause, or if there might be a delay claim against you, please call Watson & Associates, LLC to speak with any of our Federal Government Construction Attorneys at 1-866-601-5518 for a free consultation.

9 comments on “Government Construction Contract Excusable Delay Claims & FAR Changes Clause

Comments are closed.